If you've read our guide on when to upgrade your switchboard and worked through the pricing in our switchboard upgrade cost guide, there's usually one question left before booking day arrives: what actually happens once the electrician turns up? It's a fair thing to want to know in advance — your whole property loses power for part of the day, and someone is going to be working live at the one panel that everything in your home runs through. This guide walks through the appointment in the order it actually happens, so nothing on the day comes as a surprise.
Voltas Electrical & Airconditioning has carried out switchboard and electrical upgrades across Adelaide since 2010, holding licences BLD 274739 · PGE 265145 · AU 61210, with 24/7 emergency response and same-day appointments the norm. Every switchboard job we run follows the sequence below, regardless of how straightforward the board looks from the outside.
Step 1: Isolating Power to the Property
Nothing happens at the board until power is switched off. On most single-phase Adelaide homes, the electrician isolates supply at the main switch on the existing board itself, or at an external isolator near the meter if one is fitted. Where the meter itself has to be removed, resealed, or where the connection point needs work the electrician isn't authorised to touch, your electricity distributor (SA Power Networks in the Adelaide metro area) needs to disconnect and later reconnect supply at the point of attachment — your electrician arranges this as part of the job, and it's one of the reasons booking a switchboard upgrade sometimes needs a bit more lead time than a same-day call-out.
Either way, the property is left with no power for the bulk of the job. This is deliberate and non-negotiable: a switchboard has multiple live circuits feeding into it, and working on any of them safely requires the whole board to be dead, not just the circuit being touched.
Step 2: Removing the Old Board
With power confirmed off and tested dead with a proving unit, the electrician disconnects and carefully labels each circuit before removing the old switchboard enclosure. Labelling matters here — on an older home with six, ten, or more circuits, getting the labelling right the first time is what keeps the re-termination step accurate and avoids having to trace circuits again later. On boards installed before the early 1990s, this is also the point where a suspected asbestos backing sheet can be identified; if that's flagged, the job pauses for safe removal before continuing, which our guide on asbestos in old switchboards and meter boxes covers in more detail.
Booking a switchboard upgrade and want to know exactly what your specific job involves?
Get a Same-Day QuoteStep 3: Mounting and Wiring the New Board
The new enclosure is mounted, levelled, and secured to the wall or meter box frame. Inside it, the electrician installs the new main switch, circuit breakers, and safety switches (RCDs) according to the load and circuit count agreed at quoting — this is also where any extra capacity for solar, a battery, or an EV charger gets built in, if that was part of the scope. Internal wiring between the main switch, breakers, and neutral/earth bars is completed and neatly dressed inside the enclosure, since a tidy board isn't just cosmetic — it makes future fault-finding and servicing far quicker for the next electrician who opens it.
Step 4: Transferring and Re-Terminating Every Circuit
Each labelled circuit from the old board — lighting, general power, oven, hot water, ducted or split-system air conditioning, and anything else on its own circuit — is individually re-terminated onto the correct breaker or safety switch on the new board, following the layout agreed at quoting. This is usually the most time-consuming single step in the job, particularly on larger homes or where circuits weren't clearly labelled to begin with. It's also where a good electrician double-checks that circuits genuinely needing RCD protection (power and lighting circuits, under current AS/NZS 3000 requirements) actually get it, rather than simply mirroring whatever protection — or lack of it — the old board happened to have.
Step 5: Testing Every Circuit and Safety Switch
Before power is restored to the house, every circuit is individually tested — not just switched on and assumed to be fine. That includes checking correct polarity at outlets, confirming earth continuity back to the board, and measuring insulation resistance to rule out a fault hiding in the existing house wiring rather than the new board itself. Every safety switch is then trip-tested, confirming it disconnects within the required time when a test fault current is applied, exactly as it would need to during a real earth leakage event.
Only once every circuit and every safety switch passes does the electrician restore power — at the main switch, or by arranging reconnection with the distributor if that step was needed — and confirm, circuit by circuit, that everything in the house is genuinely working again: lights, power points, hot water, and air conditioning all checked, not just assumed.
Step 6: The Certificate of Compliance
The final step isn't physical work at all — it's paperwork, and it's a legal requirement, not an optional extra. A licensed electrician must lodge an electronic Certificate of Compliance (eCoC) confirming the completed switchboard work was tested and meets AS/NZS 3000, South Australia's wiring rules, verified through the Office of the Technical Regulator's eCoC system. Keep a copy of it — it's the record an insurer or a future buyer's building inspector may ask to see, and it's a different document to a broader property safety inspection report. Our guide to the Certificate of Compliance explained covers exactly what it does and doesn't cover, and who's entitled to a copy.
How Long Does the Whole Job Take?
For a standard single-phase residential switchboard in an Adelaide home, budget 4 to 6 hours from arrival to final testing — broadly consistent whether you're in an inner suburb like Norwood or further out in Aldgate. Power is typically off for 3 to 5 hours of that window, since the isolation, removal, and re-termination steps all need to happen with the board dead. That stretches out with a larger circuit count, a three-phase supply, added capacity for solar or an EV charger, wiring faults discovered once the old board is opened, or where the distributor needs to attend for a meter-side disconnection. None of that is unusual — it's exactly why the cost guide treats board access and circuit count as real price drivers, not just theoretical ones.
What to Expect Around the Power Being Off
Because the whole property loses power for most of the appointment, it's worth planning around it rather than being caught out mid-job. Move anything perishable out of the fridge and freezer in advance if the outage is likely to run toward the longer end of the window, keep phones and laptops charged beforehand, and if you rely on medical equipment, a home office server, or anything else that genuinely can't tolerate a multi-hour outage, mention it when booking so the appointment can be timed around it. Your electrician will also confirm, before switching anything off, roughly how long you should expect to be without power that day.
Frequently Asked Questions
How long does a switchboard upgrade actually take?
A standard residential switchboard upgrade in Adelaide typically takes 4 to 6 hours from arrival to final testing. A basic fuse-to-breaker swap on a small board can be quicker, while a full replacement with added circuits for solar, a battery, or an EV charger, or a job that turns up unexpected wiring faults once the old board is opened, can run longer.
Will my power be off during a switchboard upgrade, and for how long?
Yes. Your electrician (or, if the meter itself needs disconnecting, your electricity distributor) isolates supply to the whole property for the safety of anyone working on the board, so power stays off for most of the job — commonly 3 to 5 hours of that 4-to-6-hour appointment. Fridges, freezers, and anything on a UPS or battery backup are worth planning around in advance.
Does every circuit get tested before the electrician leaves?
Yes. Once every circuit is re-terminated onto the new board, a licensed electrician individually tests each circuit for correct polarity, earth continuity, and insulation resistance, then trip-tests every safety switch (RCD) to confirm it disconnects within the required time. This full round of testing is what the Certificate of Compliance is actually certifying, not just a visual check that the new board is mounted.
What is issued at the end of a switchboard upgrade?
A licensed electrician must lodge an electronic Certificate of Compliance (eCoC) for the completed switchboard work, confirming it was tested and meets AS/NZS 3000. Keep a copy — it's the record insurers and future buyers may ask to see, and it's different from a broader safety inspection report.
Ready to Book Your Switchboard Upgrade?
Get a same-day, obligation-free quote from a fully licensed Adelaide electrical team.
Sources referenced for compliance detail: AS/NZS 3000 (Wiring Rules) and energymining.sa.gov.au (SA Office of the Technical Regulator, Electronic Certificate of Compliance system).
Disclaimer: This article is provided as general information and guidance only. It draws on publicly available sources, government and industry publications (referenced where relevant), and Voltas Electrical Adelaide's own trade experience — it is not personalised advice for your specific property and does not replace a licensed, on-site assessment. Regulations, pricing, and product or brand details can change over time, so please independently verify anything relevant to your decision and seek your own professional advice before acting. To the fullest extent permitted by law, Voltas Electrical Adelaide accepts no responsibility or liability for any loss, damage, or other outcome arising from reliance on the information in this article. Where this article refers to a same-day or obligation-free quote or assessment, that refers to the quote or assessment itself — a site visit to a property well outside our normal Adelaide metro service area may incur a travel or call-out fee, as set out in our Terms & Conditions, which also has full details on the points above.